Gas network installation

Puriri Street Gas Main

150 mm and 80 mm PE gas pipeline installed through an established urban road corridor.

A staged directional-drilling installation running along Puriri Street and into Totara Street, with repeated drill set-ups, existing-service management and reinstatement through a live residential corridor.

The project involved installing a new underground gas feed from 1 to 44 Puriri Street and from 2 to 8 Totara Street in Gonville, Whanganui.

The route required a sequence of directional-drilling shots and machine repositioning through an established urban corridor, with service locating, access management, potholing and reinstatement forming part of the practical delivery.

It was not one heroic bore and a photograph. It was a staged network installation that had to keep moving through the real constraints above and below ground.

Actual work.

Enough records to prove it. Not a camera crew pretending to create it.

Holland Underground

Have another route that needs doing properly?

Send the plans, location, product details and site constraints. We will talk about the work rather than invent a photoshoot around it.